Tuesday, January 18, 2011

Closing in the Passive House - Putting on the Roof

Kilbroney Timber Frame have made great progress in the last 2 weeks. The roof is now going on, we've decided to go for a warm roof, which is unlike most Irish roofs (where the insulation is on the flat of the room ceiling) in having the insulation on the slope at rafter level. In addition the build is being made windtight ( as evidenced by all the tape) using Siga products and the roof will have a sarking board ( 9mm panelvent, a vapour diffuse wood fibre sheet) to decrease wind infiltration into the structure. Warm roofs, wind tightness and sarking board are very common techniques in Europe and Scotland but are not common in Ireland yet - I strongly suspect they will as they dramatically improve building thermal performance quite cheaply.We have used Panelvent in preference to other products due to its wind resistance and ability to release any condensation that occur ( i.e. breathability) rather than trapping it like some products like OSB do. in addition the frame is covered in breather memebrane on the outside and is windtight using siga products.

Also we're looking at the plumbing, heating and bathrooms to finalise the requirementd and get equipment and sanitaryware ordered. The windows arrive in mid February at which stage the building will be weather tight & internal works will start at pace. We even started putting in some plants last week as this is prime planting season.

Also work will be starting on running services - gas, power, comms, foul, water, stormwater - over the next few weeks now that much of the heavy vehicle movement is over and hence damage to newly buried services will hopefully be limited. Will be interesting to see how busy the services providers are at the moment & how much they will try to charge!


Monday, January 3, 2011

Passive House Self Build : Snow & Progress



Weather in Ireland in December was obviously fairly poor , now just as we start the new year we are up at tool level with all the main structural walls up and the roof, including slates, due to go up over the next few weeks. We are very happy with the quality of the structure and with the attention to detail being paid to airtightness, this should result in a good airtightness result from the preliminary test in a few months. The initial documents are going to the Passive House Institute in Germany shortly which should help smooth the process.
The windows are now due to arrive in about 6 weeks ( mid Feb) so by the end of February we will have a well sealed building and the initial internal works ( insulation, airtightness, mechanical & electrical ) will start then. A few photos of the last few weeks attached.

As the detailing of how the build is to be completed has been agreed in advance there are less variables on site. However, the protection of the airtight layer, some of which is installed as the frame is being erected, is paramount.

Sunday, November 28, 2010

still snowing & next steps

close up of the rising walls after a damp proof course applied, the frame will be going up shortly.

Also have been meeting with potential M&E contractors ( mechanical & electrical i.e. plumbing, heating, air, power, phone, data....) regarding the heating system, underfloor, solar etc...They hope to put a lot of this plant out in the garage ( actually in the roof space) which would be a great step forward. Word of warning though, these systems have to be designed by an engineer and correctly installed - secondly, in domestic situations fancy control systems , such as were ubiqutous during the celtic tiger rarely get used - lesson: make it simple to control & reliable. There is no point getting first class equipment if its not design to fit into a system for your particular house or is installed ( & commissioned) by rookies
Posted by Picasa

Wednesday, November 24, 2010

Passive House Coming out of the Ground! : Rising walls going in onto Slab




Rising walls going in on the slab; radon layer, timber frame & insulation are next. Started putting plants down on site too - its the time of year to plant those daffodils & we had received a large consignment of them.
Posted by Picasa
Part of the approach to building to passive house levels of low energy use is to agree the construction details and mateial in advance. This is particularly true where walls meet or there are unusual junctions which need to be well planned. Then on site, the qualty of workmanship  - which must tally with the agreed construction details - is vital.

Saturday, November 20, 2010

Youtube Series on designing & building a passive house - UK

An excellent 12 part series on the process of going about designing & buildings a certified passive house (PH). Called the Denby Dale house in the UK, this is the UKs first PH.

http://www.youtube.com/user/GreenBuildingStore

Friday, November 19, 2010

Windows & Slab

Foundations going in now , the weather has been great thankfully & windows being ordered today - more information on that to follow. The process of selecting a window & supplier has been a very interesting one. Ideally you would select  from  great & certified product from a supplier with a long history in Ireland & a long guarantee...but this is the ideal! We believe with Pazen ( www.pazen.eu) we have a great Irish agent, a good product at a fair price... nonetheless the price of windows for a certified passive house are astonishing

Wednesday, November 10, 2010

PHPP - what is this?

Called the PHPP, this is a detailed MS excel package with about 20 tabs whichs allows you / one to model up the energy performance using a bottom up approach by providing in the technical details for each building component e.g. local weather, window, glazing, shading , foundations, doors etc... its a very detailed package and has been proven by the PHI (Passive Haus Institute) over many years to be a great design tool. For someone who knows their way around it, there is 1-2 days of  input work. It is relatively easy to use and even takes into account summer shading from trees, impact of local terrain  etc...much of which simpler tools choose to ignore.

They key thing in using the PHPP or any such is that experience and good data inputs result in good and reliable data outputs. In our case we had the house modelled at the planning permission stage & tender stage , using standard Passive House design criteria ( air tightness, good quality windows, site shading& site aspect/building orientation)  and some design assumptions to  figure out (1) could the house be build to this standard and (2) to understand what the design & construction criteria for the actual build would be i.e. indicative U values for wall, floors, roof. Its definitely too late once the house is built or construction has started to come up with the criteria!

More over , this is the basic validation tool that the PHI require you  to  submit for certification when the building is complete.

SEAI Website - buying the PHPP:
http://www.phyxhost.ie/dev/reioshop/catalog/product_info.php?products_id=36&osCsid=aaec8343a9a9d04c455069143fc7df03

Wiki article on PassivHaus
http://en.wikipedia.org/wiki/Passivhaus

Construction Basics : Site Boundaries , foundations & progress

Well we've been in the lull period between the finishing of the site works and the house frame going up. The last few wet weeks have not had any impact as the main much shifting was already done.

Foundation will be going in shortly & will include about 400mm of insulation to get the U value down below 0.1. There are a number of proprietry foundation systems out there but the increased cost over other solutions is €10-20k; some of these sytems has potential issues with spec'ing up a high degree of radon protection ( in excess of building regulation requirements) which is a personal requirement

As regards site boundaries, advice is to get a good series of site boundary photos - in detail, including looking into ditches and hedges, before you touch anything on site. This type of information can made a real difference should any dispute arise during the build or later

Sunday, September 26, 2010

Mmore digging

Well... there has been a lot more digging onsite, retaining wall & materials have now been purchased. Setting out the sites took a lot longer than expected, was connect to where is the centre of a hedge etc... but that is nearly resolved.

Tuesday, September 21, 2010

Progress in mid sept - muck & walls!

Well the last few weeks have been all about digging & shifting muck. We have to put in a retaining wall & decided against straight concrete for aesthetic & cost reasons. In the end we chose a segmented retaining wall i.e. an engineered concrete block, that looks vaguely like cut stone - photos to follow once its put up next week. Final setting out of the road & services will happen shortly & the site is really starting to take shape.